Gateshead HEIGHTS - Fabric Works

Meeting: 14/03/2017 - Cabinet (Item 197)

197 Fabric Works and HEIGHTs Combined Delivery proposal pdf icon PDF 254 KB

Report of the Strategic Director, Communities and Environment

Minutes:

Consideration has been given to the award of a construction contract to Wilmott Dixon Construction via the SCAPE Major Works Framework, for delivery of  fabric works to be undertaken alongside the High Rise Energy Infrastructure for Gateshead Housing Tenants(HEIGHTs) project comprising:

 

  • Window replacement for all Harlow Green high rise blocks
  • Façade replacement and replacement windows at Regent Court.

 

RESOLVED -

(i)

That the entering into a delivery agreement with Wilmott Dixon Construction via the SCAPE Major Works Framework, for combined delivery of the HEIGHTs project and associated fabric measures be approved.

 

 

 

 

(ii)

That delegated authority be given to the Strategic Director, Communities and Environment, following consultation with the Strategic Director, Corporate Resources, to agree the final terms, scope and costs of the contract awards.

 

 

 

The above decisions have been made for the following reasons:

 

 

 

 

(A)

To continue to deliver Council priorities around reducing fuel poverty, energy consumption and sustaining tenancies.

 

 

 

 

(B)

To maximise efficiencies through combining fabric improvements with ERDF grant funded works that will support capital investment as part of the Council’s Capital Programme.

 

 

 

 

(C)

To improve the Council’s assets and ensure that the Council’s Housing stock remains fit for purpose and deliver a sustainable HRA.