Issue - meetings

Clasper Village Housing Development - Scheme and Estimate

Meeting: 16/07/2019 - Cabinet (Item 44)

Clasper Village Housing Development - Enabling Works Contract

Report of the Acting Strategic Director, Communities and Environment

Minutes:

Consideration has been given to a proposal to enter into a contract with Wates Construction Ltd. (WCL) for the enabling works and site remediation ahead of delivery of the residential development and regeneration of the former Clasper Village housing site.

 

RESOLVED -            (i)        That the entering into a contract with WCL be                                                    approved , via the Scape Framework for the site                                               enabling works up to the value of £6.7m and                                                   the Service Director, Council Housing, Design and                                        Technical Services be authorised to place an order                                          for the works, subject to the form and content of                                               the contract being approved by the Strategic                                                   Director, Corporate  Services and Governance in                                              accordance with the Constitution.

 

(ii)        That the total scheme cost estimates be noted and                  further reports be received on the next phase of                        delivery.

 

                                    (iii)       That the Service Director, Council Housing, Design                                         and Technical Services be authorised to progress                                            the scheme and to establish full contract estimates                                                for the construction works and sales and marketing                                               activity to deliver the housing development.

 

The above decisions have been made for the following reasons:

 

                                    (A)       To promote the accelerated delivery of homes                                                  within the Borough.

                                   

                                    (B)       To help meet housing need in the Borough.

 

                                    (C)      To realise the Council’s policies and objectives in                                             relation to housing growth.